Analysis of Project Management

Total Length: 1063 words ( 4 double-spaced pages)

Total Sources: 1+

Page 1 of 4

Business (Project Management)

Make vs. Buy Decision Tree Analysis

A great deal of the process and practice of risk management encompasses delving into the future, making an attempt to comprehend what might take place and whether it is of significance. The decision tree analysis is incorporated and contained within the PMBOK® Guide as one of the methods of project management and quantitative risk analysis (Hutlett, n.d). In definition, a decision tree is a graphical demonstration of conceivable resolutions to a decision centered on a number of particular situations and circumstance. It is termed a decision tree as it commences with a single root, which thereafter diverges and divides into a number of resolutions, similar to the way a tree has branches. There is great benefit and advantage that decision trees offer (Milosevic, 2003). This is because not only are they beneficial graphics that facilitate in perceiving what one thinks, but also because forming a decision tree necessitates a methodical, acknowledged thought process (Goodpasture, 2004). Time and again, the major restraint of our decision making is that we can only choose from the acknowledged substitutes. Decision trees assist in formalizing and reinforcing the brainstorming procedure so we can ascertain more prospective resolutions (Goodpasture, 2004).

Risk is defined as an event that has a probability of occurring, and could have either a positive or negative impact to a project should that risk occur. Project risk is one of the hardest project components to plan for and the project contains significant risks as well as already being behind schedule (Project Management Institute, 2013).


The main utility of decision trees is to consolidate the planning process of arriving at a decision. Since at the beginning of a project, the risk variable is highest, all factors that might or might not occur need to be accounted for and provisions thereto made, keeping the actual financials in view. External risks that might occur by way of new taxation issues, the volatility of the currency value, and regulatory norms and statutes may arise at any stage of the project cycle. The internal risks are generally taken care of through fixed contract pricing to reduce the effect of variations. The advantage of the project under consideration is that environmental issues, leanings towards newer (and latest and improved) technology and increased demand support the cause of product sales, making it easier to arrive at the financial decision. As a thumb rule, the way of arriving at the total cost of risk is by first ascertaining the cumulative sum of possibility of each potential risk and then adding all such individual factors, followed by multiplying this value with the consequences of the risk occurrences. One important aspect while accounting for risks is to minimize the effect of any negative impact of a risk wherever applicable. This is achieved by maximizing the positive outcomes of any risk occurrence while in the planning stage. The strategy used for diluting the negative impacts and extracting the maximum….....

Show More ⇣


     Open the full completed essay and source list


OR

     Order a one-of-a-kind custom essay on this topic


sample essay writing service

Cite This Resource:

Latest APA Format (6th edition)

Copy Reference
"Analysis Of Project Management" (2015, October 14) Retrieved May 20, 2025, from
https://www.aceyourpaper.com/essays/analysis-project-management-2155971

Latest MLA Format (8th edition)

Copy Reference
"Analysis Of Project Management" 14 October 2015. Web.20 May. 2025. <
https://www.aceyourpaper.com/essays/analysis-project-management-2155971>

Latest Chicago Format (16th edition)

Copy Reference
"Analysis Of Project Management", 14 October 2015, Accessed.20 May. 2025,
https://www.aceyourpaper.com/essays/analysis-project-management-2155971