Concert Pavilion in the Park Project Organization: Essay

Total Length: 948 words ( 3 double-spaced pages)

Total Sources: 0

Page 1 of 3

Concert Pavilion in the Park

Project Organization:

Project Manager:

Project Manager's Responsibilities

Oversight of all procurement and construction, ensuring all inspections and sign-offs, approving bids or sub-contracted work, ensuring completed project meets expectations of client group.

Executive Sponsor:

Smith Sundecks

Develop the WBS and Schedule:

Task ID

Start Date

Duration

Predecessor Tasks *

Inspection of site

hours

P1

Obtain permit for grading

hours

Review blueprints

hours

Review vendor bids for foundation

1-hour

Select, hire, & meet with vendor for foundation

hours

Inspect finished foundation

1-hour

Review bids for framing of pavilion & roofing

5/5/2012

hours

I1, I2

V4

Select, hire, & meet with vendor for framing

5/15/2012

hours

I1, I2

I3

Inspect completed framing & roofing

5/30/2012

hours

I1, I2

V5

Review vendor bids for electrical connections

5/15/2012

1-hour

I1, I2, I3

V6

Select hire, and meet with vendor for electrical connections

5/20/2012

4 hours

I1, I2, V4

I3

Inspect electrical connections with officials

6/5/2012

2 hours

I1, I2, V6

V7

Review vendor bids for gutters, drains, and landscaping.

6/5/2012

4 hours

I1, I2, I3

V8

Select hire and meet with vendor for gutters, drains, and landscaping

6/10/2012

8 hours

I1, I2, V6

I4

Inspect gutters, drains, and landscaping. Test drains.

6/15/2012

4 hours

I1, I2, V8

Analyze Resources

Task ID

Material Resources

Work (Human) Resources

I1

N/A

Jones & Dear

P1

Permit paperwork & approved blueprints

Jones

Approved blueprints

Jones, Rigby, & Dear

V1

Vendor bids

Mills

V2

Grading equipment, forms, concrete

Mills, Dear, Mays, Vendor employees 2 to 3

I2

Permit paperwork

Jones, Dear

V3

Vendor bids

Mills

V4

Lumber, nails, scaffolding, underlayment

Dear, Vendor employees 3 to 4, Mays

I3

Permit paperwork

Jones, Dear

V5

Vendor bids

Mills

V6

Shingles, underlayment, vents, tarps, shingles transport system

Dear, Vendor employees 2 to 3, Mays

I3

Permit paperwork

Jones, Dear

V7

Vendor bids

Mills

V8

Gutters, gravel, wiring & fixtures, backhoe

Dear, Vendor employees 4 to 6

I4

Permit paperwork

Jones, Rigby, Dear, & Mays

Which resource(s) is (are) doing the most work?

On-site, David Dear reports directly to the Project Manager.

Stuck Writing Your "Concert Pavilion in the Park Project Organization:" Essay?

Off-site, communication flows through Ellen Rigby. Rigby is responsible for bringing client request and expectations to Ed Jones for engineering approvals. Rigby is also responsible for interpreting any official or engineering constraints to the client group. Martin Mills is responsible for keeping the project on budget and must keep Ellen Rigby up-to-date on costs and expenditures. Mills and Sally Mays together address the project's fiscal reports. David Dear conveys any potential or real irregularities in planning or budget to Rigby, who then addresses the issues with the appropriate supervisor. Rigby and Jones are peers with regard to authority and responsibility, each in their respective areas.

Are there any resources that have been overlooked (for example, could any of these tasks be outsourced to another division or even consultants?)

The project is….....

Show More ⇣


     Open the full completed essay and source list


OR

     Order a one-of-a-kind custom essay on this topic


sample essay writing service

Cite This Resource:

Latest APA Format (6th edition)

Copy Reference
"Concert Pavilion In The Park Project Organization " (2011, July 31) Retrieved May 19, 2024, from
https://www.aceyourpaper.com/essays/concert-pavilion-park-project-organization-85037

Latest MLA Format (8th edition)

Copy Reference
"Concert Pavilion In The Park Project Organization " 31 July 2011. Web.19 May. 2024. <
https://www.aceyourpaper.com/essays/concert-pavilion-park-project-organization-85037>

Latest Chicago Format (16th edition)

Copy Reference
"Concert Pavilion In The Park Project Organization ", 31 July 2011, Accessed.19 May. 2024,
https://www.aceyourpaper.com/essays/concert-pavilion-park-project-organization-85037