Decision Making and Planning in Construction

The formula to determine the most probable to complete the backyard swimming pool is as follows:

Where

a = Optimistic

m = Most probable

b =Pessimistic

The study uses Microsoft Excel software to calculate the probable time for the project. The results show that the project will be complete within 49.5 days, which is approximately 50 days as revealed in Table 1 below.

Activity

Immediate Predecessor

Duration in Days

Optimistic

Most Probable

Pessimistic

Expected Time

Project Schedule

The study uses the Microsoft Excel to develop the project schedule and output is revealed below:

The PERT distribution to complete the project is in Fig 1 as follows

Fig 1: PERT Distribution to Complete the Project

The stimulation to determine the expected time to complete the Swimming Pool project with 90% confidence is as follows:

Activity

Variance

Variance

A

(6-3)/36 0,08

B

(6-2)/36

0,11

C

(7-5)/36

0,06

D

(10-7) /36

0,08

E

(6-2)/36

0,11

F

(3-1)/36

0,06

G

(10-5)/36

0,14

H

(10-6)/36

0,11

i

(5-3)/36

0,06

Total

0,81

The next is to find the Standard Deviation (SD), which is the square root of the variance as follows:

Thus, Square root of 0.81 =0.90 days.


Thus, there is 90% confidence that the project will complete at expected time.

3. What is the estimated probability that the project can be completed in 25 or fewer days?

The critical part of the project is A-C-F and expected time is 12.83. The variance is 0.20, and the standard deviation is 0.44. Thus, P (X 25) is 65%.

Problem II

Activity

Optimistic

Most Probable

Pessimistic

Expected Times

Variance

A

4.0

5.0

6.0

B

2.5

3.0

3.5

C

6.0

7.0

8.0

D

5.0

5.5

9.0

E

5.0

7.0

9.0

F

2.0

3.0

4.0

G

8.0

10.0

12.0

H

6.0

7.0

14.0

Optimistic

Most Probable

Pessimistic

Expected Time

Variance

a m

b

A

4

5

6

5,00

0,06

B

2,5

3

3

2,92

0,01

C

6

7

8

7,00

0,06

D

5

5,5

9

6,00

0,11

E

5

7

9

7,00

0,11

F

2

3.....

     Open the full completed essay and source list


OR

     Order a one-of-a-kind custom essay on this topic


sample essay writing service

Cite This Resource:

Latest APA Format (6th edition)

Copy Reference
"Decision Making And Construction" (2017, April 04) Retrieved May 21, 2025, from
https://www.aceyourpaper.com/essays/decision-making-construction-2164996

Latest MLA Format (8th edition)

Copy Reference
"Decision Making And Construction" 04 April 2017. Web.21 May. 2025. <
https://www.aceyourpaper.com/essays/decision-making-construction-2164996>

Latest Chicago Format (16th edition)

Copy Reference
"Decision Making And Construction", 04 April 2017, Accessed.21 May. 2025,
https://www.aceyourpaper.com/essays/decision-making-construction-2164996