Energy Technology Data Centre Migration Work Breakdown Case Study

Total Length: 1269 words ( 4 double-spaced pages)

Total Sources: 3

Page 1 of 4

Energy Technology Data Centre Migration

Work Breakdown Structure

Network Diagram

Critical Tasks (Highlighted)

Milestones

Resources Assigned

Quality

Cost

Reporting

Brian Smith, who is a network administrator at Advanced Energy Technology (AET) has been tasked with moving a large data centre to a new office location in the newly developed industrial complex at the Corvallis International Airport in Corvallis, Oregon. The company provides application as a service product to two hundred thirty five oil jobbers and gasoline companies. As a result, the company can experience no downtime during the transition to the new facility. Any user interruptions from clients could result in lost revenues and damage to the company's reputation as a reliable IT company in the industry.

The scenario in this case dictates the entire focus of the project. Since the data center components must all be moved in a weekend after the new location is prepared then there is not any allowance for error. This coupled with the fact that the organization will not tolerate any inconvenience to the clients makes a successful transfer even more salient. Therefore the most important aspect to this project will undoubtedly be thorough risk management and risk planning. A careful evaluation will have to be conducted by each of the functional representatives as well as a risk contingency plan be prepared to avoid any potential delays.

Work Breakdown Structure

Task Name

Duration

Preliminary Discussions

1 day

Scope Meeting

1 day

Initial Project Planning

2 days

Hire Contractor

5 days

Network Design

10 days

Order Hardware (Ventilation)

15 days O

Stuck Writing Your "Energy Technology Data Centre Migration Work Breakdown" Case Study?

rder Hardware (Racks, Servers, Switches, and thers)

10 days

rder Hardware (Power Supplies)

5 days

Install Ventilation

5 days

Install Racks

15 days

Construction

20 days

Inspection

2 days

Install Power Supplies and Run Cables

5 days

Functional Unit Approval

5 days

Check Voltage

1 day

Install Test Servers

5 days

Batteries, Vents, Test Servers

2 days

Primary Systems Check

1 day

Set fficial Date

1 day

Move Network Components

2 days

Network Diagram

Critical Tasks (Highlighted)

Task Name

Duration

Start

Finish

Predecessors

Preliminary Discussions

1 day

Mon 5/28/12

Mon 5/28/12

Scope Meeting

1 day

Tue 5/29/12

Tue 5/29/12

1

Initial Project Planning

2 days

Wed 5/30/12

Thu 5/31/12

2

Hire Contractor

5 days

Fri 6/1/12

Thu 6/7/12

3

Network Design

10 days

Fri 6/1/12

Thu 6/14/12

3

rder Hardware (Ventilation)

15 days

Fri 6/15/12

Thu 7/5/12

5

rder Hardware (Racks, Servers, Switches, and thers)

10 days

Fri 6/15/12

Thu 6/28/12

5

rder Hardware (Power Supplies)

5 days

Fri 6/15/12

Thu 6/21/12

5

Install Ventilation

5 days

Fri 7/6/12

Thu 7/12/12

6,11

Install Racks

15 days

Fri 7/6/12

Thu 7/26/12

7,11

Construction

20 days

Fri 6/8/12

Thu 7/5/12

4

Inspection

2 days

Fri 7/6/12

Mon 7/9/12

11

Install Power Supplies and Run Cables

5 days

Tue 7/10/12

Mon 7/16/12

12

Functional Unit Approval

5 days

Tue 7/17/12

Mon 7/23/12

13

Check Voltage

1 day

Tue 7/17/12

Tue 7/17/12

13

Install Test Servers

5 days

Wed 7/18/12

Tue 7/24/12

15

Batteries, Vents, Test Servers

2 days

Wed 7/25/12

Thu 7/26/12

16

Primary Systems Check

1 day.....

Show More ⇣


     Open the full completed essay and source list


OR

     Order a one-of-a-kind custom essay on this topic


sample essay writing service

Cite This Resource:

Latest APA Format (6th edition)

Copy Reference
"Energy Technology Data Centre Migration Work Breakdown" (2012, May 27) Retrieved May 20, 2025, from
https://www.aceyourpaper.com/essays/energy-technology-data-centre-migration-80321

Latest MLA Format (8th edition)

Copy Reference
"Energy Technology Data Centre Migration Work Breakdown" 27 May 2012. Web.20 May. 2025. <
https://www.aceyourpaper.com/essays/energy-technology-data-centre-migration-80321>

Latest Chicago Format (16th edition)

Copy Reference
"Energy Technology Data Centre Migration Work Breakdown", 27 May 2012, Accessed.20 May. 2025,
https://www.aceyourpaper.com/essays/energy-technology-data-centre-migration-80321