Project Management the First Activity Case Study

Total Length: 464 words ( 2 double-spaced pages)

Total Sources: 2

Page 1 of 2

5

The pathway a-D takes 21 weeks; C-E takes 20 weeks; B. takes 8 weeks.

To crash by one week, reduce F. To 5 weeks at a cost of $30 direct costs.

To crash by two weeks, reduce F. To 5 weeks @ $30; reduce D. By 1 week @ $50.

To crash by three weeks, reduce F. By 1 week @ $30; reduce D. By 2 weeks @ $100; reduce C. By 1 week @ $40. This way, a-D takes 19 weeks; C-E takes 19 weeks.

Stuck Writing Your "Project Management the First Activity" Case Study?



To crash by four weeks, reduce F. By 1 week @ $30, reduce D. By 2 weeks @ $100; reduce a by 1 week @ $80; reduce C. By 1 week @ $40; reduce E. By 1 week @ $100.

To crash by five weeks, reduce F. By 1 week @ $30; reduce D. By 2 weeks @ $100; reduce a by 2 weeks @ $160; reduce.....

Show More ⇣


     Open the full completed essay and source list


OR

     Order a one-of-a-kind custom essay on this topic


sample essay writing service

Cite This Resource:

Latest APA Format (6th edition)

Copy Reference
"Project Management The First Activity" (2010, February 27) Retrieved May 19, 2024, from
https://www.aceyourpaper.com/essays/project-management-first-activity-175

Latest MLA Format (8th edition)

Copy Reference
"Project Management The First Activity" 27 February 2010. Web.19 May. 2024. <
https://www.aceyourpaper.com/essays/project-management-first-activity-175>

Latest Chicago Format (16th edition)

Copy Reference
"Project Management The First Activity", 27 February 2010, Accessed.19 May. 2024,
https://www.aceyourpaper.com/essays/project-management-first-activity-175