Earned Value Management Research Paper

Total Length: 1616 words ( 5 double-spaced pages)

Total Sources: 4

Page 1 of 5

Validating the Concept of Earned Value Management

It is important to note, from the onset, that most companies have in the past made extensive use of planned costs and actual costs in seeking to track project costs. In this case, if all the funds assigned to a specific project are used up, then the target is seen as having been hit. However, a cost under-run is perceived is less funds are spent than had been allocated. Similarly, we have an overrun situation whenever more is used than had been allocated. Although this approach has been used extensively in the past, it is important to note that it does not take into consideration the value of work performed – which is a critical dimension that ought not to be ignored.

The relevance of earned value management (EVM) cannot be overstated in the measurement of project progress as well as performance. EMV, in the words of Carroll (2017), “provides a way of keeping control of a project and illustrating its progress towards completion in terms of work and value (cost)” (102). In essence, it is important to note that amongst other things, EVM comes in handy in facilitating the measurement of work that has actually been undertaken in a project setting. As Flemming and Koppelman (2010) point out, EVM has gained widespread usage overtime. In general, those that embrace EVM are able to have access to timely data that enables management to not only evaluate progress, but also institute the relevant corrective measures if need be. Thanks to EVM, senior managers also have access to summary reports.

It should also be noted that one of the key components of EVM is project baseline. This is more so the case given that it is deemed to be a critical point of reference for the various activities related to EVM. The data EVM provides for project decision making purposes is largely quantitative. In basic terms, therefore, EVM systems provide answers to some basic project management questions. In relation to a specified project, the project manager does have insight on where they have been, the present status, and where they are headed.

In seeking to validate the concept of EVM, it would be prudent to highlight some of its benefits. As a matter of fact, EVM has a wide range of benefits that transcend the concepts of budgetary allocations.
Unlike is the case with traditional management, EVM has several sources of data. Via the incorporation of these data sources, EVM enables the comparison of the scheduled work’s budgeted value with not only the completed work’s actual value but also what Fleming and Koppelman (2010) refer to as “the EV of physical work completed” (74). Thus, in comparison to normal project tracking, EVM enables project managers to have access to more useful information – and as a result, they are able to determine whether or not the project is at the desired point and the timelines with regard to completion. With EVM, it is possible to not only have better control the various activities of the project, but also a more enhanced visibility of the same (Fleming and Koppelman, 2010). On this front, emerging issues can be addressed early enough so as to ensure that the project progresses without any major hiccups and is completed in good time. In instances where EVM is not utilized, it may not be possible to chart the project status in an informed and accurate manner.

EMV should, in essence, be seen as an approach towards sound project management practices. This is particularly the case given that as Garrett (2011) observes, with EVM, it is possible for the project manager to determine or assess the much that has been achieved so far in an objective and informed manner. It is also important to note that with EVM, as has been pointed out elsewhere in this text, it is possible to forecast the future with a higher degree of certainty. This is made possible via an analysis of the much that been achieved so far. Further, the information provided by EVM can be presented in an easy to grasp graphic format. This is particularly important given the need to ensure that all the stakeholders are well briefed on the various specifics and aspects of the project or undertaking. With this information, stakeholders can be able to determine whether or not the project is giving them value for money.

According to Garrett (2017), the fact that EVM effectively fulfills the role of an early problem detection system further underlines its relevance. When problems are identified early enough, it….....

Show More ⇣


     Open the full completed essay and source list


OR

     Order a one-of-a-kind custom essay on this topic


sample essay writing service

Cite This Resource:

Latest APA Format (6th edition)

Copy Reference
"Earned Value Management" (2018, August 04) Retrieved June 17, 2024, from
https://www.aceyourpaper.com/essays/earned-value-management-2173234

Latest MLA Format (8th edition)

Copy Reference
"Earned Value Management" 04 August 2018. Web.17 June. 2024. <
https://www.aceyourpaper.com/essays/earned-value-management-2173234>

Latest Chicago Format (16th edition)

Copy Reference
"Earned Value Management", 04 August 2018, Accessed.17 June. 2024,
https://www.aceyourpaper.com/essays/earned-value-management-2173234